RF/2026/03Under way · first year

Off-grid solar for far hamlets

Photograph from Off-grid solar for far hamlets
Focus area
Location
Lawngtlai district, Mizoram
Three hamlets, installed in sequence
Term
18 months · February 2026 to July 2027 · month 8 of 18
Budget
₹1,15,00,000 committed · ₹41,00,000 spent to 31 August 2026
Funding
A single institutional funder, disbursing against milestones
Expected reach
104 households connected of 310 planned

Why this work

What the project does

Load and willingness-to-pay survey completed in all three hamlets
Household solar with battery storage sized to lighting, phone charging and a fan — 104 systems installed
One shared cold storage unit per hamlet, for produce and vaccines; first unit running since July 2026
Two trained and paid local technicians per hamlet, with a stocked spares box; two certified so far
A village-set tariff covering maintenance, held in a village account and collected monthly
Public performance data: uptime and revenue posted in the village each quarter

Timeline

Feb 2026
Hamlet shortlist confirmed with the zonal office
Complete
Apr 2026
Installer appointed by open tender
Complete
Jun 2026
First hamlet installed and metered
Complete
Jul 2026
First cold storage unit commissioned
Complete
Dec 2026
Second hamlet installed; four technicians certified
In progress
Jul 2027
Third hamlet complete; one-year uptime review published
Scheduled

What we will measure

Indicator
Target
Achieved
Households with reliable evening power
104
System uptime since commissioning
97%
Trained technicians retained locally
2
Maintenance cost covered by village tariff
64%
Post-harvest loss reported by users
too early to report

Who runs it

Energy lead
Full time · in post since January 2026
Technical adviser
Consultant · monthly site visits
Community organiser
One position · district based
Monitoring & documentation
Shared across programmes

Partners

Zonal electricity office; an installer selected by open tender in April 2026

Safeguarding & monitoring

All field staff work under the foundation's child protection and grievance policies. Data is collected against the indicators above, reviewed twice a year with the community, and published in the annual report whether or not it is flattering.

Documents

Load and tariff survey, 2026
Published
Tender documents and award note
Published
Quarterly uptime report, Q2 2026
Published
Expenditure statement to Aug 2026
On request

This project is running, and open to scrutiny.

We will share the full project report, expenditure statements and monitoring data with any serious enquiry, and we are content to be diligenced hard. Visits to the site can be arranged.

Talk to us about this project