RF/2026/04Under way · first year

Landslide early warning on the Serchhip road

Photograph from Landslide early warning on the Serchhip road
Location
Serchhip district, Mizoram
Seven settlements along 41 km of the state highway
Term
30 months · March 2026 to August 2028
Budget
₹68,00,000 committed · ₹19,00,000 spent to 31 August 2026
Funding
State disaster management authority, with a matching CSR grant
Expected reach
Roughly 4,300 people who use the road daily

Why this work

What the project does

Twelve tipping-bucket rain gauges and six slope inclinometers installed along the known failure zones
Rainfall thresholds derived from ten years of district closure records
A named warden in each of the seven settlements, trained and on a monthly stipend
SMS and phone-tree alerting that works without data coverage
Two rehearsed closures a year, before and during the monsoon

Timeline

Mar 2026
Agreement signed with the district authority
Complete
Jun 2026
Failure-zone survey and threshold model published
Complete
Sep 2026
First eight gauges live and reporting
In progress
May 2027
All wardens trained; first rehearsed closure
Scheduled
Aug 2028
Handover of the network to the district authority
Scheduled

What we will measure

Indicator
Target
Achieved
Instrumented failure zones
8
Median warning time before a closure
too early to report
Settlements with a trained warden
3 of 7
Alerts reaching households within 30 minutes
61%

Who runs it

Programme lead
Full time · in post since February 2026
Geotechnical adviser
Consultant · quarterly site visits
Community organiser
One position · resident in Serchhip
Monitoring & documentation
Shared across programmes

Partners

District disaster management authority; seven village councils; a geotechnical group at the state university

Safeguarding & monitoring

All field staff work under the foundation's child protection and grievance policies. Data is collected against the indicators above, reviewed twice a year with the community, and published in the annual report whether or not it is flattering.

Documents

Failure-zone survey, 2026
Published
Rainfall threshold model
Open licence
Expenditure statement to Aug 2026
On request

This project is running, and open to scrutiny.

We will share the full project report, expenditure statements and monitoring data with any serious enquiry, and we are content to be diligenced hard. Visits to the site can be arranged.

Talk to us about this project